Cosntruction of the Grev Kafi Museum
|
|
|
The main stages of construction of the Grev Kafi Museum:
- In October 2014, the project was approved by the Department of Architecture of Chisinau mayor’s office (
Proiect vizat).
- In May 2015, the project has been approved by the National Council for the Historical Monuments of the Ministry of Culture of the Republic of Moldova (
Proiect executiv).
- In September 2015, the building permit has been received (
Autorizatie de construire) from the Department of Architecture of Mayor’s office in Chisinau.
- On 24th October 2015 began the construction of the Grev Kafi Museum.
By September 2017, the team has managed to fundraise ~35.000 US Dollars.

Summer 2015

October 2015

December 2015

August 2016

June 2017

September 2017